2020 Bond Progress

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
2020 bond a change you can see

On March 10, 2020, voters in the Plymouth-Canton Community Schools’ communities passed the 2020 Bond. This bond addresses facility and site improvements, equity of facilities, enhances safety and security throughout the school district, furniture and playground upgrades, school bus purchases, and addresses imminent infrastructure and technology needs at most facilities. The district is able to maintain the existing school debt levy (4.02 mills) and offered this bond proposal with ZERO INCREASE to the current tax rate. The total bond issue cost is $275 million.

Estimated ZERO INCREASE to the current annual debt millage rate: With the approval of the bond, it is estimated that the annual debt millage required to repay the District’s outstanding and the proposed bonds will remain at or below the current debt millage rate of 4.02 mills. 

The 2020 Bond touches every building in the District with a focus on creating equity across all schools, addressing imminent building and site infrastructure issues, enhancing learning spaces through both remodeling and building, and upgrading technology throughout the District.

2020 Bond - Construction Updates 

POWERPOINT PRESENTATION on 2020 BOND SCHEDULE REVIEW 

-from the Board of Education meeting held October 10, 2023

2020 Bond Schedule- REVISED as of 9/8/2023

------------------------------------------------------------------------------------------------------

Weekly Update on Completed and Current Projects:

Bid Package #EL-1 - Dodson, Eriksson, Field, and Hulsing - Weekly Progress  - COMPLETED SPRING 2022

Bid Package #HS-1 - Salem Auditorium Addition and Renovation - Weekly Progress Reports - COMPLETED WINTER 2022

Bid Package #EL-2 - Bird, Miller, and Smith - Weekly Progress Updates - COMPLETED FALL 2023

Bid Package #HS-2 Plymouth Natatorium and Multipurpose Addition - Weekly Progress Reports

Bid Package #EL-3 - Isbister Elementary - Weekly Progress Updates 

Bid Package #MS-1 - Pioneer Middle School - Weekly Progress Updates

Bid Package #HS-3 - Starkweather Academy - Weekly Progress Updates

Bid Package #HS-4/P-CEP-1 - Canton HS Addition, Renovation, and New Stadium - Weekly Progress Updates

Bid Package #HS-2a - Plymouth HS Band Room Addition